icon_widget_image Mon - Fri 8:00 - 17:30; Sat & Sun - CLOSED icon_widget_image 61053 PR 207, Sunnyside, Manitoba, Canada R5R 0C1 icon_widget_image 2490 Gottselig Road, RM of Sherwood, SK S4K 0A6 icon_widget_image 9919 Biggs Ave, Fort McMurray, AB T9H 1S2 icon_widget_image 1(877)9-SERVCO (1-877-973-7826) icon_widget_image info@servcocanada.com
Image Alt
Explore The Future

KCS / RCS

KCS / RCS

Project Details

Full scope of work included design assist development of 3D model, quality control, Fire Alarm Vesda System, Building Management system, Lightning Protection, Grounding / Shielding, Construction temporary lighting/ power/ heating, Interior Telecommunication, Interior lighting /power Commissioning, Security System, install of mechanical equipment, Piping and ducting insulation and cladding, Chilled water system, Glycol Cooling System, Valve Cooling system, Hydro Testing, permits.

Overview

In 2016, 2017, 2018 ServcoCanada (formerly DMS Industrial Constructors) provided base building infrastructure installation for Mechanical, Piping, Heat Tracing, Insulation, HVAC, Electrical Distribution, DC Systems for Distribution Protection and Control, Lighting and Life Safety Systems for Manitoba Hydro’s New Riel and Keewatinohk Convertor Station Bipole III Transmission Reliability Project.

Part of the Bipole III transmission project that links power generated from the lower Nelson River area and delivers to the distribution system in Southern Manitoba. The Riel and Keewatinohk stations convert high voltage alternating current to high voltage direct current and vice versa. Converting to HVDC allows much lower electrical losses over vast distances than standard AC transmission. ServcoCanada (formerly DMS Industrial Constructors) held a critical role in the construction of both converter stations electrical and mechanical systems. This was a design build project ServcoCanada (formerly DMS Industrial Constructors) worked closely with the design team to help finalize the design and execute their scope of work.

Actual Location : Riel Converter Station Winnipeg Manitoba, Keewatinohk Converter Station 725 km north of Winnipeg and 79 kms Northeast of Gillam Manitoba

 

 

Work Completed By

Related Services

Project Info

Client: KCS / RCS

SCOPE OF WORK: Supply and Install Building Heating, Ventilation, Air Conditioning, Process Piping, Mechanical, Plumbing, Controls, Electrical work

Completed: September 2018